Project overview
Banks Ave, Pagewood NSW 2035
We are delivering 224 new social and private market homes across 3 buildings in Pagewood. This project will increase housing supply in the area and contribute to a more diverse and inclusive community.
We will deliver this project in 2 stages. Stage 1 will deliver 84 well-designed social homes across a single 7-storey building. Stage 2 will deliver 140 private homes across two 8-storey buildings.
The project will also include:
- landscaped gardens that make a positive contribution to the area and streetscapes.
- a shared community room for social housing residents.
- basement car parking and internal lifts.
- fencing across the site.
Current status
The NSW Department of Planning, House and Infrastructure (DPHI) approved this project on 11 August 2026.
We prepared a 'Response to Submissions' report that explains the feedback received and how it was considered. You can read the report on the DPHI website.
Next steps
We are preparing for construction of Stage 1 of this project with demolition of 78 and 80 Banks Avenue expected to start in late 2026. We have partnered with Traders in Purple to manage construction of the new homes.
Construction of Stage 1 is due to start in early 2027 and be completed by mid-2029.
These timeframes may be subject to change due to weather and other circumstances.
Contact Homes NSW
For more information or to speak to a member of the Homes NSW Community Engagement team:
- email communityengagement@homes.nsw.gov.au
- call us on 1800 738 718 and leave a message on our voicemail so we can call you back.