Decision summary
| Business | MCP Projects Pty Ltd |
| Registration number | BUP0000983 |
| Monetary penalty | $20,000 |
| Effective date | 11 May 2026 |
| Related practitioner | Mark Akkari |
| Current Design and Building Practitioner registration | View DBP registration |
| Related action under the Home Building Act 1989 | View contractor record |
Disciplinary ground and summary
Ground 1: Design and Building Practitioners Act 2020 (DBP Act)
Contravention of the DBP Act, namely a breach of a stop work order issued under section 89 of the Act.
Objective severity: Minor
The contravention related to limited remedial works and was not extensive. The conduct of the practitioner was negligent and there was no apparent financial gain because it appears that the purpose of the work was to ensure compliance with applicable building standards.
Disciplinary action
- under section 66(1)(c) of the Design and Building Practitioners Act 2020 (NSW), make a determination requiring MCP Projects Pty Ltd to pay a penalty in the sum of $20,000.00 within the period set out on the face of the penalty notice.
- under section 66(1)(d) of the Design and Building Practitioners Act 2020 (NSW), impose the following conditions on registration BUP0000983 in the name of MCP Projects Pty Ltd:
- each Director of the Authority Holder, or any Director who is appointed after the date of this decision, must, within six (6) months of date of this decision or their appointment complete and pass the following education and training:
- the UTS short course Advanced Building Regulation (or a successor course or equivalent course offered by same institution) (or equivalent course offered by another institution as agreed by the Secretary in writing); and
- the SAI Global course Foundation and Implementing a Quality Management System ISO 9001:2015 (or a successor course or an equivalent course offered by same institution) (or equivalent course offered by another institution as agreed by the Secretary in writing).
- store and maintain records of compliance with conditions (1)(a) and 1(b) and provide those records within seven (7) business days on request by the Secretary.
- each Director of the Authority Holder, or any Director who is appointed after the date of this decision, must, within six (6) months of date of this decision or their appointment complete and pass the following education and training:
Related practitioner
Mark Akkari
Registration number
BUP0004040
Relationship to this decision
On 15 April 2024, MCP Projects Pty Ltd (MCP), as the building practitioner for a development at 46 & 48 Holden Street Gosford NSW (Development), breached a Stop Work Order (SWO) that had been issued in relation to that development.
Under section 95 of the Design and Building Practitioners Act 2020, the director of MCP, Mr Akkari, is taken to have also contravened section 89 of the Act.
Disciplinary outcome
Monetary penalty and conditions imposed on registration
View the disciplinary action against Mark Akkari.