Issued under Section 38 of the (Compliance Residential Apartment Buildings and Enforcement Powers) Act 2020
Richmond Rose Bay Pty Ltd (ACN 636 583 581) (the Developer) is issued with this Modified Stop Work Order (this Order) in relation to residential apartment building located at 6-8 Richmond Road, Rose Bay NSW 2029 (Lot 1 DP 436354) (the Building).
On the 07 July 2023 the NSW Building Commissioner, David Chandler, as delegate for the Secretary issued a Stop Work Order in accordance with section 29 of the Residential Apartment Buildings (Compliance and Enforcement Powers) Act 2020.
On the 29 January 2024 the Building Commission NSW issued the First Modified Stop Work Order to include item 16(d) which permitted precautionary testing at No. 10 Richmond Road, Rose Bay.
On the 31 January 2024 the Building Commission NSW issued the Second Modified Stop Work Order to include No. 4 Richmond Road, Rose Bay.
On the 14 March 2024 the Building Commission NSW issued the third Modified Stop Work Order to include No. 4 Richmond Road, Rose Bay.
This fourth Modified Stop Work Order has been issued to allow the next stage of work to commence as detailed in the letter titled “Request for Modified Stop Work Order at 6-8 Richmond Road, Rose Bay” issued by Rothshire engineers dated 15 July 2024 with reference number 2324109-LET-003-R2.
Issued on: 7 July 2023
Modified on: 30 July 2024