August 2025 Eurobodalla Regional Hospital construction update
Concrete works continue, window and cladding installation has started, internal stud walls and services are going in and roundabout works are continuing.
Construction on the new hospital is moving ahead with exciting progress on site.
Concrete works are continuing and the team is getting ready for the next big pour. Windows are now being installed, starting in the maternity and paediatrics areas. Cladding has also begun, marking the first stage of the building’s façade.
The last of the ground preparation has been completed, sealing the exposed area underneath the building and preparing the site for the final wing.
Inside, stud walls and services are now being installed.
The final stair and lift core has been poured, and scaffolding and formwork in that area will soon be removed. The concrete structure at the main entrance is also complete and the area is taking shape.
At the roundabout, the rock and drainage layers have been installed, providing a solid foundation and ensuring effective water drainage as construction continues. Works will now begin to prepare the area for pavement installation.
There are currently around 250 workers on site, and the project has just reached a major 1 year milestone with over 235,000 hours of work completed so far.