Finley Health Service - Update December 2025
Services are continuing at the Finley Health Service during construction works.
Please note the following changes:
- temporary closure of part of the driveway and some car spaces adjacent to the former physiotherapy room (old ED) to enable Stage 2 works to continue,
- the central corridor (eastern end) is closed while Stage 2 works are completed,
- the physiotherapy service has moved to a temporary location in the Community Health building until project completion,
- the Fitpack machine and community sharps bin has relocated to the front of the Community Health building until project completion,
- the outpatient X-ray service has temporarily relocated to Tocumwal Health Service until the completion of the project. The mobile x-ray machine will continue to provide some imaging for emergency presentations and inpatients at Finley Health Service. Please make appointments directly with the Finley Health Service on (03) 5883 9100.
Thank you for your patience as we complete these important works for the redevelopment.
Roofing and internal works progressing
Work completed since construction started in mid-2025 includes re-roofing the eastern end of the hospital and minor internal works.
Stage 2 works underway now include re-roofing the central area of the hospital, and internal works to prepare for stage 3 works commencing in early 2026.
Stage 3 includes construction of the new inpatient wing and is expected to commence in early 2026. More information will be provided about access changes before the start of works.

To receive the latest project updates by email, please sign up here.