Resident Update - Northeast Building Construction and Parking Program - Albury Wodonga Regional Hospital Project
Health Infrastructure and Albury Wodonga Health thank you for your patience as we progress the construction of the Northeast Building and a range of on-site car parking works to support the construction of a new and modern health facility.
There has been a lot of construction activity on-site over the last few months and we appreciate the impact and potential disruption this work can cause.
Please contact our Project Team to raise a specific concern at the details below.
The Northeast Building construction – What to expect
Since planning approval for the Northeast Building was received in August 2025, construction has been moving at pace. Due for completion in late 2026, this purpose-built facility will house key health services currently located in the existing Allied Health Building.
The new two-storey building is starting to take shape, with construction crews progressing structural steel installation, including wall panels and lift shaft pilings.
Parking will increase on the Hospital campus
Health Infrastructure and Albury Wodonga Health are working closely with the builder to manage parking and traffic changes to support construction while maintaining access to hospital services. A staged approach to parking delivery is being rolled out as we aim to minimise disruption while impacting parking availability over time.
Over the next six months you can expect the following:
- 120 parking spaces will progressively open from along Borella Road. 60 spaces opened on Monday 1 June with the remaining 60 to be released from mid-June
- Approximately 50 spaces will return for public use when the Key Health Worker Accommodation Project site compound is removed in late June.
- Upgrades to the East Street mid verge will open 25 permanent spaces to the public in August with additional East Street verge upgrades releasing a further 75 permanent spaces.
- Car park expansion, at the southern end of the Hospital near the Emergency Department scheduled for later in the project, is now planned for delivery in early 2027.
- A further 40 spaces will become available in late 2026 on completion of the Northeast Building and the removal of the construction compound.
What this means is that more parking will be available on the hospital campus, with the long-term plan providing around 1000 parking spaces for the Albury Hospital campus.
How will the work affect you?
The health and safety of the local community is our top priority. We recognise that construction works can be disruptive to local residents, businesses, road users, hospital staff, patients, and visitors. We place the impact on these groups at the centre of how we plan and manage all construction activities.
The project team is constantly monitoring and managing site access points and may implement short term traffic control management and speed limit reductions when required. For your safety, please follow the directions of traffic controllers at all times. More information about how we manage construction impacts can be found on the project website.
Keeping you informed
If you would like to speak with a member of the project team directly, you can call us on our project information line on (02) 9978 5402 or email us at HI-Albury@health.nsw.gov.au or go to the project webpage.