Status: In progress
About the project
The NSW Government has committed $6.7 million for the development of a new synthetic athletics track at Sydney Academy of Sport, Narrabeen. The project will support users from grassroots to elite across a range of sports.
Scope
The project scope includes:
- a new World Athletics (WA) compliant synthetic athletics track with moisture resilient track surface
- new asphalt sub-base
- drainage and stormwater system upgrades
- accessibility improvements.
Forecast project timeline
July 2025
- Delivery team established including appointment of NSW Public Works as project manager and SPORTENG as Principal Design Consultant.
- Planning pathway determined.
- Preparation of Review of Environmental Factors (REF) commenced.
- Preliminary site investigations completed.
December 2025
- REF approved.
December 2024
- Concept design consultation.
August 2025
- Concept design finalisation.
- Detailed design commenced.
October 2025
- Detailed design concluded.
October 2025
- Main works construction contractor procurement commenced.
December 2025
- Main works construction contractor procurement concludes.
January 2026
- Site establishment and track installation construction commences.
Quarter 4 2026
- Operational readiness commences.
January 2027
- Site works and track installation conclude.
- Project handover and completion.