Funding is available under 6 funding streams: a planning stream, 4 implementation streams and one for emergency actions identified in certified emergency action sub plans following a significant erosion or coastal inundation event.
More about Coastal and Estuary Planning & Implementation 2024-25
August 2025
What was approved
Approved for Eurobodalla Shire Council
Beach scraping is proposed over a stretch of Surfside’s eastern beach as emergency coastal protection of a severely damaged dune in accordance with the Coastal Zone Emergency Action Subplan. The works aim to rebuild and enhance the dune and protect the foredune system as well as the reserve.
$15,083 was approved by
Minister for the Environment & WaterDate approved
August 2025Location of the recipient
EurobodallaAbout the grant
Applications approved
1
Applications received
1
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
July 2025
What was approved
Approved for Shoalhaven City Council
This project will deliver the following action from Coastal Zone Emergency Action Subplan Shoalhaven Open Coast and Jervis Bay CMP. Beach scraping activities will place sand on the existing revetment as well as at the northern section to build up the toe of the bank to encourage development of an incipient foredune in this area.
$25,320 was approved by
Minister for the Environment & WaterDate approved
July 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
1
Applications received
1
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
May 2025
What was approved
Approved for Liverpool City Council
This project will prepare and deliver the Coastal Management Program (CMP) Stages 2-4 for the Georges River estuary. The CMP encompasses the foreshore of the river estuary, including tributaries, and the southern and western foreshores of Botany Bay that are primarily under the control of participating councils and state agencies.
$665,601 was approved by
Minister for the Environment & WaterDate approved
May 2025Location of the project
Bayside, Campbelltown, Canterbury-Bankstown, Fairfield, Georges River, Liverpool, Sutherland ShireLocation of the recipient
LiverpoolAbout the grant
Applications approved
1
Applications received
1
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
April 2025
What was approved
Approved for Port Macquarie Hastings Council
This project intends to prepare and deliver Stage 3 and 4 of the Coastal Management Program (CMP) process, allowing Port Macquarie Hastings Council to submit a CMP for certification to provide a long term, coordinated strategy for managing the coastal zone.
$196,667 was approved by
Minister for the Environment & WaterDate approved
April 2025Location of the project
Port Macquarie-HastingsLocation of the recipient
Port Macquarie-HastingsAbout the grant
Applications approved
1
Applications received
1
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Nambucca Valley Council
The Nambucca Heads Break wall is a high use public reserve which is being impacted by erosion from both riverine and open coast processes. The intention of this project is to assess all environmental processes affecting the site and determine the best possible option with the greatest environmental, asset protection and user-friendly functionality for the remediation of the reserve.
$156,980 was approved by
Minister for the Environment & WaterDate approved
April 2025Location of the project
Nambucca ValleyLocation of the recipient
Nambucca ValleyAbout the grant
Applications approved
1
Applications received
1
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
March 2025
What was approved
Approved for Ballina Shire Council
A floating boom will be purchased and installed at the northern end of Lake Ainsworth and aquatic weeds will be removed with a harvester, in addition spot treatment of remaining aquatic weeds will be undertaken over two years.A floating boom will be purchased and installed at the northern end of Lake Ainsworth and aquatic weeds will be removed with a harvester, in addition spot treatment of remaining aquatic weeds will be undertaken over two years. The control of aquatic weeds will result in protected cultural, public amenity and environmental values of the Lake.
$30,167 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
BallinaAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Ballina Shire Council
The project will be located at Lake Ainsworth and closely surrounding lands in Lennox Head. The project aims to investigate and implement a culturally informed method of acknowledging and building awareness of the significant Aboriginal cultural and heritage values of the Lake and improve the future management of the Lake by implementing strategies that include and reflect the needs of local Aboriginal people.
$130,401 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
BallinaAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Bega Valley Shire Council
This project involves works across both dune and riparian areas. It will include weed control and revegetation of coastal and riparian areas which are in a degraded state and vulnerable to erosion due to the impacts of costal hazards. This work will help to strengthen these natural systems and restore environmental value to withstand impacts into the future.
$90,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Bega ValleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Bellingen Shire Council
This project will focus on the conservation of threatened shorebird species within Bellingen Shire’s coastal environment zone which includes beaches, dunes, estuaries and wetlands. The aim of the project is to identify shorebird species, quantify populations, map critical habitats and assess threats.
$60,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
BellingenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Central Coast Council
The proposed project sites are located across the Central Coast local government area with activities prioritising the removal of weed species to aid regeneration of native plant communities. The overall condition of the proposed locations has deteriorated with reduced biodiversity and by removing invasive species native plant communities then have the opportunity to regenerate, and ecosystem services enhanced.
$86,980 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Central CoastAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for City of Newcastle
The objectives of this project are to facilitate the delivery of sand scraping activities at Stockton Beach to enhance immediate coastal protection through building the upper profile and dune system, building coastal resilience reducing the need for reactive emergency response works. The project extent of the site for the proposed beach scraping works is the southern portion of Stockton Beach, which falls under the Newcastle local government area, from the northern breakwater in the south to Corroba Oval in the north.
$260,001 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
NewcastleAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Clarence Valley Council
This project will implement instrumentation and monitoring improvements, geotechnical investigations and slope stability measures to address the slope instability issue at Pilot Hill, Yamba. The improvements, along with weed management and coastal habitat restoration, will provide contemporary accurate monitoring data of land movement and groundwater at Pilot Hill informing ongoing risk assessment and future management actions.
$270,001 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Clarence ValleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Clarence Valley Council
This project will review, evaluate and introduce new planning controls to address coastal hazard risks. The project will encompass the coastal zone along the Clarence Valley coastline as identified in the Open Coast CMP. The outcomes will be implemented through local planning instruments such as development control plans to mitigate current and future risk from coastal hazards.
$69,999 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Clarence ValleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Clarence Valley Council
This project will place additional sand into the Wooli Beach dune system increasing the resilience of the dune to erosion and recession. Dune rehabilitation and revegetation will further increase the resilience of the dunes, improve biodiversity values, and public amenity and safety.
$66,665 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Clarence ValleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Kiama Municipal Council
This project aims to restore Bangalay Sand Forest EEC and surrounding vegetation at Seven Mile Beach Reserve through development of a restoration works plan and associated targeted weed control for the site. The project will conduct targeted weed control across 18 ha of bushland reserve and will monitor and evaluate progress through photo point monitoring.
$36,667 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
KiamaAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Kiama Municipal Council
This project will result in increased resilience to coastal hazards and will inform strategic assessments and guide future management of council owned asset. Detailed evaluations with structural assessments will be conducted for three key assets to be utilised for the purpose of updating asset management plans and providing strategic direction for managing hazards in the future.
$90,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
KiamaAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Kiama Municipal Council
This project will build increased preparedness and resilience to coastal hazards through the preparation of designs and necessary approvals in readiness for interim coastal protection works at priority high risk locations to facilitate construction if triggers are reached for action to be undertaken. Additional project activities include Church Point geotechnical investigations and the installation of citizen science beach monitoring initiatives like Coast Snap to involve the community in monitoring coastal morphology across the LGA.
$234,845 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
KiamaAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Lake Macquarie City Council
This project involves rehabilitating a riparian corridor within the coastal zone at Wyee Point. The site contains an endangered ecological community, River-flat Eucalypt Forest on coastal floodplains, and pockets of saltmarsh and mangrove. The project seeks to rehabilitate the riparian vegetation using best practice bush regeneration techniques, remove weed threats, and protect exposed Aboriginal sites.
$130,267 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Lake MacquarieAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Mid-Coast Council
This project will implement the retrofit of the Wingham Wetland, a key stormwater treatment asset in the Manning River catchment. The retrofit will upgrade critical components like the gross pollutant trap , sediment basins, and macrophyte zones. Once complete, the improved wetland will better filter stormwater runoff, reduce nutrient and sediment loads, and enhance the ecological health of the Manning River Estuary.
$642,831 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Mid North CoastAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Nambucca Valley Council
This project is located in Bowraville on the southern tributary to the Nambucca Estuary. The project will encompass installation of rock toe protection, riparian restoration and large camphor laurel removal, large wood debris placement for stabilisation/ habitat and riparian fencing. The project will restore and protect the riparian habitat around the town and also enhance public accessibility to the river.
$243,220 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Nambucca ValleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Northern Beaches Council
This project aims to manage the most northern dune bay at North Avalon Beach through sand scraping, reducing beach erosion due to ongoing impacts from climate change induced storm events, formalising access by restoring access fences, and dune stabilisation with wind erosion control and replanting with native coastal vegetation.
$32,653 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Northern BeachesAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Northern Beaches Council
This project supports the issues raised in the coastal dunes management strategy for Freshwater Beach to achieve reduced sand blow-outs, improved dune condition by weed control and revegetating with native coastal species, and formalising pedestrian movements through dune systems. The aims of the project include fencing to formalise access and exclusion areas for revegetation, returning loose sand to the foredune/beach area with sand scraping, and reducing erosion with sand trapping fencing and coir logs.
$24,895 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Northern BeachesAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Port Stephens Council
The ongoing shoreline erosion at Corlette Beach presents a risk to public safety and impacts recreational access and amenity of the beach. This project will perform sand carting and enable gradual transportation eastward in front of Conroy Park.
$75,667 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Port StephensAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Port Stephens Council
This project will undertake the carting of sand from the western beach section and nourishment of the eroding sections of Shoal Bay Beach to improve beach access and amenity. Drone and bathymetric survey activities will measure the impact of the works and will help understand its effectiveness.
$178,001 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
Port StephensAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
This project will undertake a coastal processes and coastal hazards study of the Callala Bay foreshore area and Currarong Beach to better determine coastal hazard risk and coastal processes to support the scientifically based derivation and assessment of coastal management solutions. A detailed options assessment will also be completed based on the updated site understanding
$146,667 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
The Callala Bay Sailing School is a high value public asset considered to be exposed to a high level of coastal erosion risk. The existing coastal protection works are comprised of informal and ad hoc placement of rock bags requiring investigation and design of a replacement structure. This scope of works includes foreshore survey and geotechnical investigations, and preparation of a detailed design for future coastal protection works.
$50,001 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
This project involves the review and update of all Council asset management plans (AMPs) relevant to the coastal zone, as well as the development and implementation of a monitoring program designed to assess and track the condition of various coastal assets and infrastructure. This project will support Council in aligning the relevant AMPs with the objectives and outcomes of the CMP and ensure that Council are able to establish a monitoring program to adequately and proactively respond to the management of coastal hazards risks affecting infrastructure and assets in the coastal zone.
$100,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
This project involves the investigation of potential management options for addressing estuary entrance instability at Mollymook Beach, Manyana Beach, and Hyams Beach. The project will involve a feasibility assessment of potential management options.
$26,666 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
This project will implement high priority stormwater management actions from the Shoalhaven hydraulic impact assessment that was completed as part of the CMP development. The project will upgrade the stormwater network in areas where uncontrolled runoff poses a significant threat to property and safety at Vincentia, Berrara and Narrawallee. Council will also include several dune restoration works to adjacent foreshore areas.
$205,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
This project will conduct formal coastal engineering condition inspections and assessment of several existing coastal protection structures across the Shoalhaven LGA involving the Shoalhaven Heads Surf Club rock revetment, existing coastal protection works at Kioloa and the Princes Highway at Ulladulla Harbour. The outcome of these assessments will result in a clear understanding of the nature and extent of maintenance works required to maintain protection and function at these locations.
$70,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
Ongoing erosion observed at Lions Park, Burrill Lake, is steadily increasing and impacting on a popular recreational foreshore area and key assets. This erosion has been occurring due to increased tidal conveyance through the entrance and has been exacerbated during periods of high tides and large ocean events. This project will use beach scraping from the adjacent extensive flood tide delta shoals to nourish the foreshore and manage the erosion impacts to the foreshore vegetation and road.
$37,500 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Shoalhaven City Council
Works will restore the foreshore and address underlying stormwater erosion issues along the Boat Harbour Beach foreshore in Bendalong. The works will comprise of enhancement of the foreshore through revegetation and formalisation of beach access, demolition of existing stormwater pipes and associated headwall and the installation of new stormwater pipes and scour protection. The enhancement of the foreshore aims to provide the long-term resiliency from erosion from storm events.
$276,667 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
ShoalhavenAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Wollongong City Council
This project will strategically engage with communities in high-risk areas of the lake, to build awareness of coastal processes and future hazards, and support resilience and capacity building to address future climate challenges. Using the Lake Illawarra community engagement and participation strategy, this program will align community support with values in implementing CMP actions as a means to strategically address and respond to climate change impacts into the future.
$126,059 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
WollongongAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Wollongong City Council
This project will improve bank stabilisation, water quality and erosion protection of Lake Illawarra and creek line areas of Barrons Gully and Brooks Creek by planting endemic species for bank support and filtration of water. The removal of weeds and revegetating the reserves will diversify and expand native vegetation communities and help with providing habitat for local fauna.
$260,000 was approved by
Minister for the Environment & WaterDate approved
March 2025Location of the recipient
WollongongAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
December 2024
What was approved
Approved for Coffs Harbour City Council
This project will enable Council to commence stages 2-4 of the City of Coffs Harbour open coast CMP. The CMP will establish management actions and a long-term strategy for the coordinated management of the Coffs Harbour open coast.
$253,335 was approved by
Minister for the Environment & WaterDate approved
December 2024Location of the recipient
Coffs HarbourAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Sydney Coastal Councils Group Inc
This project will commence Stages 2-4 of the Outer Sydney Harbour CMP, covering Port Jackson and Middle Harbour. The CMP will address a range of coastal management issues along the harbour foreshore and identify actions to develop a long-term strategy for the outer Sydney Harbour coastal zone.
$369,121 was approved by
Minister for the Environment & WaterDate approved
December 2024Location of the recipient
SydneyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
October 2024
What was approved
Approved for Mid-Coast Council
This project will consolidate and convert three expired coastal zone management plans into a CMP and aim to provide a robust management framework for the Mid-Coast coastal area for the next decade. Additionally, the project will update hazard modelling in discrete locations using Probabilistic Hazard Modelling techniques, ensuring a consistent approach to coastal management in the Mid-Coast coastal area.
$244,793 was approved by
Minister for the Environment & WaterDate approved
October 2024Location of the recipient
Mid North CoastAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25
What was approved
Approved for Waverley Council
This project will enable Council to undertake the stage 2 studies identified in the Waverley Beaches CMP stage 1 - Scoping Study. These studies, which include a coastal risk assessment, seawall condition assessments, a coastal inundation damages assessment, and a geotechnical risk assessment, are identified as critical components in developing a technically robust and comprehensive CMP.
$313,334 was approved by
Minister for the Environment & WaterDate approved
October 2024Location of the recipient
WaverleyAbout the grant
Applications approved
33
Applications received
43
Coastal and Estuary Planning & Implementation 2024-25
Agency funding this grant
The Department of Climate Change, Energy, the Environment and WaterProgram term
3 yearsMore about Coastal and Estuary Planning & Implementation 2024-25