Project overview
Belmore Rd, Riverwood NSW 2210
What’s happening
Following extensive community consultation, we have scaled back the proposed redevelopment of the Riverwood housing estate. This decision aims to provide better:
- outcomes for social housing residents
- alignment with community expectations.
The new proposal will deliver 420 homes. This includes 50% social and affordable housing. It will be delivered with minimal impact on existing infrastructure.
Next steps
Homes NSW is gauging market interest before we prepare the tender process for a developer. We will look for a development partner who can:
- progress the development application
- assist with the delivery of new homes.
There will be future community consultation opportunities as part of this process.
If the development application is approved it will include:
- the realignment of Virginia Place
- moving overhead power lines underground
- the potential for new retail premises.
A new childcare centre will replace the existing one, located close to the original site.
If you have any questions, please contact the Community Engagement team:
- phone 1800 738 718 (voicemail)
- email communityengagement@homes.nsw.gov.au.
Planning process and timeline
The Riverwood estate renewal is a long-term project. It will be delivered in stages over the next 15 to 20 years. This timeline outlines:
- what has happened so far
- what is happening now
- when we expect the project to be delivered.
We are committed to providing the community with regular updates throughout this time.
2016-2021
- We consulted with key stakeholders and the community.
- We had extensive community consultation on a draft master plan.
- We prepared technical studies and supporting documentation.
2022-2023
- We placed the rezoning proposal on public exhibition for feedback.
- Homes NSW lodged a response to submissions (RTS).
2024
- We held the public exhibition of the revised rezoning proposal.
- The Department of Planning, Housing and Infrastructure (DPHI) approved the rezoning proposal.
2025
- Gauge market interest for a developer.
- Prepare a 'Request for Proposal' (RFP) tender.
2026
- Tender released to market.
- Developer appointed.
- Development application lodged.
2027
- Determination of Development Application announced.
- If approved, construction will commence.
2028-2043
- Continuous review of the future masterplan for the wider estate will happen.