Working hours
Our light rail construction work mostly occurs during the following standard hours:
- 7am to 7pm Monday to Friday
- 8am to 6pm on Saturday, with exceptions in some areas.
Typically, the light rail construction crews do not work on Sundays or public holidays.
When we need to work at night (usually between 7pm and 7am), works will be carried out for a maximum of 4 nights in a 7-day period.
Westmead
Day works
Location | Works | Dates |
---|---|---|
Hawkesbury Rd | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Hainsworth St | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Bridge Rd | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
Carlingford stop to Westmead stop | maintenance and repairs | Monday 9 September - Sunday 15 September |
Night works
Location | Works | Dates |
---|---|---|
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
North Parramatta
Day works
Location | Works | Dates |
---|---|---|
Church St between Factory and Market St | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
Night works
Location | Works | Dates |
---|---|---|
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
Prince Alfred Square stop to Ngara stop | Overhead wiring inspection | Monday 9 September - Sunday 15 September |
Carlingford stop to Westmead stop | maintenance and repairs | Monday 9 September - Sunday 15 September |
Parramatta CBD
Day works
Location | Works | Dates |
---|---|---|
Church St | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Macquarie St | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Tramway Ave | Testing at light rail stops, rail inspection | Monday 9 September - Sunday 15 September |
Barrack Lane | Completion of pit drainage | Monday 9 September - Sunday 15 September |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
Night works
Location | Works | Dates |
---|---|---|
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 9 September - Sunday 15 September |
Camellia to Carlingford
Day works
Location | Works | Dates |
---|---|---|
Carlingford stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Telopea stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Dundas stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Yallamundi stop (Rydalmere) | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Rosehill Gardens stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Stabling and maintenance facility | Fit-out of buildings, commissioning of light rail vehicles | Monday 9 September - Sunday 15 September |
Night works
Location | Works | Dates |
---|---|---|
Carlingford stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Telopea stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Dundas stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Yallamundi stop (Rydalmere) | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Rosehill Gardens stop | Testing at stops, light rail vehicle testing | Monday 9 September - Sunday 15 September |
Stabling and Maintenance Facility | Fit-out of buildings, commissioning of light rail vehicles | Monday 9 September - Sunday 15 September |
Carlingford stop to Rosehill Gardens stop | Overhead wiring inspections | Monday 9 September - Sunday 15 September |
Road closures and traffic changes
(week ending Sunday 15 September 2024)
Light rail vehicle testing
Traffic control will be in place to manage traffic and pedestrians along the whole alignment from 6am – 6pm Monday - Friday.