Working hours
Our light rail construction work mostly occurs during the following standard hours:
- 7am to 7pm Monday to Friday
- 8am to 6pm on Saturday, with exceptions in some areas.
Typically, the light rail construction crews do not work on Sundays or public holidays.
When we need to work at night (usually between 7pm and 7am), works will be carried out for a maximum of 4 nights in a 7-day period.
Westmead
Day works
Location | Works | Dates |
---|---|---|
Hawkesbury Rd | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Hainsworth St | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Bridge Rd | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
Carlingford stop to Westmead stop | Maintenance and repairs | Monday 2 December - Sunday 8 December |
Night works
Location | Works | Dates |
---|---|---|
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
North Parramatta
Day works
Location | Works | Dates |
---|---|---|
Church St between Factory and Market St | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
Prince Alfred stop to Ngara stop | Overhead wiring works | Monday 2 December - Sunday 8 December |
Night works
Location | Works | Dates |
---|---|---|
Carlingford stop to Westmead stop | Maintenance and repairs | Monday 2 December - Sunday 8 December |
Tramway Avenue to Westmead | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
Prince Alfred stop to Ngara stop | Overhead wiring works | Monday 2 December - Sunday 8 December |
Parramatta CBD
Day works
Location | Works | Dates |
---|---|---|
Church St | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Macquarie St | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Tramway Ave | Testing at light rail stops, rail inspection | Monday 2 December - Sunday 8 December |
Barrack Lane | Completion of pit drainage | Monday 2 December - Sunday 8 December |
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
Night works
Location | Works | Dates |
---|---|---|
Tramway Avenue to Westmead stop | Light rail vehicle testing | Monday 2 December - Sunday 8 December |
Camellia to Carlingford
Day works
Location | Works | Dates |
---|---|---|
Carlingford stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Telopea stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Dundas stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Yallamundi stop (Rydalmere) | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Rosehill Gardens stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Stabling and maintenance facility | Fit-out of buildings, commissioning of light rail vehicles | Monday 2 December - Sunday 8 December |
Rosehill Gardens to Carlingford | Overhead wiring works | Monday 2 December - Sunday 8 December |
Night works
Location | Works | Dates |
---|---|---|
Carlingford stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Telopea stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Dundas stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Yallamundi stop (Rydalmere) | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Rosehill Gardens stop | Testing at stops, light rail vehicle testing, overhead wiring works | Monday 2 December - Sunday 8 December |
Stabling and Maintenance Facility | Fit-out of buildings, commissioning of light rail vehicles | Monday 2 December - Sunday 8 December |
Carlingford stop to Rosehill Gardens stop | Overhead wiring works | Monday 2 December - Sunday 8 December |
Contact us
To find out more about the project, or if you would like to discuss your preference for work hours, please call our 24/7 community information line on 1800 139 389.